The Tale of the Temporary Cement Floor
At the suggestion of our landscaper, we extended the cement floor at our backyard. I thought it was a great idea - it wouldn't be muddy going to the outdoor sink, and there would be a bit more space for other things like a small grill.
Unfortunately, with just a little bit of rain, water started pooling at the newly cemented area. So with the typhoon season now in full swing, we were facing the possibility of our ground floor getting flooded before we even moved in! Our contractor's solution? Create a hole at the bottom of the wall, and have the water drain out to the neighbor's backyard... Unbelievable, but true.
The ones over at Reach Out and Build apparently did not bother to check the house plans, or look around to see if there was a storm drain nearby before constructing the cement floor. The thing is, when I once complained about how badly the carport was built, one of the founders, Sir Buddy, cut me off and told me that he was an expert.
Wouldn't an expert know how things might end up by studying the area? And if he wasn't sure, wouldn't he first consult the blueprints or ask the village management about how the house works? Well, none of that happened. They only decided to physically check and consult the village engineer after I got mad at them.
And that was how we found out that all the houses built by Avida do not have gutters, and none are connected to the village storm drains. The rain from the roof just falls to the ground and the water is not directed elsewhere. It is up to the homeowner to build a drainage system, which according to the village manager, will cost around Php 100,000.
Earl said that he's tired of all the expenses and just wants to move in, so we had the cement floor removed. Though we were warned that it won't make much of a difference as that area is lower than the rest of the property, and with the walls now bordering the house, the water will have nowhere else to go.
So that was a complete waste of time and money - all of which could have been avoided had our contractor been an actual expert. Because if he really knew what to do, he could have recommended that the cement floor would not be a good idea. Or to suggest building the storm drain along with the fence so that the yard won't collect water every time it rains.
Time to buy a submersible pump?
10 July 2017
Repairs, Etc.
We're now halfway through the process of making the house livable. The carport still isn't finished, but they've started on the other items on our to-do list:
A recent finding was that some of the exterior window frames, which are made of wood, have rotted and need to be replaced.
But since our contractor made a mistake with the polycarbonate roof, we've decided to compromise. We'll keep the lighter colored roof in exchange for four of the windows being repaired free of charge. We've also decided to have all the window frames replaced for a uniform look and we were thinking that it's just a matter of time before the others follow the rotted path.
Honestly, I would rather have the darker polycarbonate roof as it will give a little bit more shade. Earl, however, doesn't want to spend any more than we already have. Though maybe it was a good thing that they made a mistake since we're getting a discount on the window frames?
A recent finding was that some of the exterior window frames, which are made of wood, have rotted and need to be replaced.
But since our contractor made a mistake with the polycarbonate roof, we've decided to compromise. We'll keep the lighter colored roof in exchange for four of the windows being repaired free of charge. We've also decided to have all the window frames replaced for a uniform look and we were thinking that it's just a matter of time before the others follow the rotted path.
Honestly, I would rather have the darker polycarbonate roof as it will give a little bit more shade. Earl, however, doesn't want to spend any more than we already have. Though maybe it was a good thing that they made a mistake since we're getting a discount on the window frames?
23 March 2012
Sixteen Centimeters
The line you see above is exactly 16 cm - that's the distance between the bedroom door (at an open angle) and the our current queen-sized bed (if we decide to bring it with us).
Queen Bed Option
Almost a year ago, I made a post about how measuring our room made me gloomy. The master's bedroom in the model unit (which you can view here) is much larger than the actual space turned over to us - take note that the bed you see in the picture is bigger than ours and there's even space for two night tables!
Well, it has been said that when life hands you lemons, make lemonade. So last week, I decided to take a second look. I must admit I was feeling optimistic - maybe I made a mistake the first time, maybe the room would miraculous expanded on it's own... Alas, it was not to be. If we were to keep our current bed frame (161 cm x 201 cm), then one person would need to walk sideways just to get to their side.
Full/Double Bed Option
So now we're starting to think of buying a full/double bed instead, but that would mean giving up six (6) inches on the width. The length will be the same as apparently Ambassador Beds just vary on the width (both their full and queen-sized beds are 190 cm long).
This then begs the question: Should we go for sleep comfort or more walking space?
12 June 2011
"Fixed"
More paint has been peeling around the house and this time, it's the door jambs. We've been advised that the reason behind this is because the metal door frames were not primed before they were painted. The primer that should have been used is either colored red or gray so if the paint were to peel, we would not be seeing metal right away.
When we informed Avida of this, they agreed with the findings of our contractor and promised to fix things.
That was a month ago. Last Friday, after numerous follow-ups, Avida finally showed up at the house and below is a picture of their handiwork:
I'm a bit clueless when it comes to the technicalities of house painting, but shouldn't the primer be applied first before painting over it again? Another question we have is, why didn't they do the entire area instead of just a spot here and there?
We are waiting (again) but this time for Avida to "fix" things before our contractors can finish up at the house.
When we informed Avida of this, they agreed with the findings of our contractor and promised to fix things.
That was a month ago. Last Friday, after numerous follow-ups, Avida finally showed up at the house and below is a picture of their handiwork:
I'm a bit clueless when it comes to the technicalities of house painting, but shouldn't the primer be applied first before painting over it again? Another question we have is, why didn't they do the entire area instead of just a spot here and there?
We are waiting (again) but this time for Avida to "fix" things before our contractors can finish up at the house.
01 April 2011
25 October 2010
Paint Job Review
Last week, Maricel asked me if Avida was going to finish painting the window casings outside. She explained that it looks as if they had just done one coat of paint.
I mentioned this to Des from the head office and Engrs. Frolan and Mark when they went to the house last Thursday to check on the problematic bathroom sinks (which you can read about here). Frolan immediately said that it was already finished and asked me, "the house was turned over to you, right?" in Filipino. I felt a tinge of sarcasm in his tone. I maybe sensitive when it comes to the house but I think I know when someone is being sarcastic. Let's just say, I use sarcasm quite often...
I pointed out the areas Maricel described, he started inspecting it in places I never thought of, and declared that Maricel was right! Further checks outside revealed that the paint in other areas were either peeling or bubbly. To think that it has only been four months since the house was turned over to us...
Engr. Mark commented that the reason for the peeling and the bubbles was that the paint had not been mixed well. I said, "Wasn't it Avida that did the painting?" And he gave me a sheepish smile and said that this was under Rommel's jurisdiction.
As to the sinks, Engr. Frolan advised that they will fix the ground floor bathroom sink but that Avida is "just accommodating" us. He further explained that since we signed a waiver due to the non-installation of the bathroom tiles, the sink was technically for our account.
First of all Frolan, we never signed a waiver and we have it in writing that we only asked Avida not install the bathroom tiles. It was a surprise to us that they didn't install the sinks and the toilets.
Second, Ellen advised that we should have told Avida that the sink and toilet installation was for a later date. Uh, we've already paid the plumber. Shouldn't we have been informed of this from the beginning?
Third, we got the standard unit which includes bathroom and sink installation. This means it's already paid for.
To Frolan and Rommel, I am sure we will all get along sometime in the future. But at the moment I just don't see that happening especially if you talk to us like we owe Avida a favor.
Try looking at things from our perspective because from all accounts, it's Avida that owes us big time.
In the meantime, please fix the house. Because if there was nothing wrong with the place, then I would not need to call you. Now wouldn't the thought of NOT seeing me be incentive enough to do things correctly this time?
20 October 2010
As Per Plan
The drain hole for the sink in the upstairs bathroom is askew. This means that the sink is not centered and thus it's at the side of the wall. I asked Engr. Rommel if he would do the same arrangement in his house and he replied in Filipino that it did seem wrong. His actual words were "parang mali, noh?" But he said Avida can't fix it as it's "as per plan."
The bathroom sink downstairs is also positioned similarly. Avida installed the drain hole in such a way that the sink is now BLOCKING THE BATHROOM DOOR. Was that "as per plan" too? Just a thought.
Note that we did not mess with the drain holes. Ellen from Avida head office, told me earlier today that this situation is due to our contractors. I had to point out that we "borrowed" one of the plumbers from the neighboring house that is currently being built so technically he's not our contractor, he's THEIR contractor. And he only placed the sink over the drain hole made by Avida.
We found out about the sink blocking the door last Saturday because as mentioned in the previous post, the house was turned over without the sinks and toilets installed.
All this resulted in my temper going over normal levels (yet again) with Engr. Rommel in attendance. I asked him why we had to spend a lot on cement just so that we could install tiles properly? A few days prior, he said he would fix the situation. I asked him why he only offered to fix it now when we alerted him to the problem during the house inspection (which you can read about here)? Why only now when we've already done the repairs ourselves?
I told him that I was not mad at him personally but he's the representative of Avida. (I didn't bother to add that since he's from the Construction Group, he was responsible for overseeing how the house was built.)
My voice broke when I talked to him as I really felt like crying. I pointed out to him that we have spent so much just fixing everything from the floor to the electrical system only to have water go down the switches. He said it was fine and that nothing was damaged. I countered that, sorry but I do not trust Avida.
I have come to the conclusion that the ones who say "everything will be fine" obviously are not paying for the house.
Last Monday afternoon and early Tuesday morning, I tried calling Engr. Rommel to get an update. After 15 tries, he had yet to answer his phone. This was unusual as he used to answer right away or he would call or text back to inquire what I needed. Now, zilch.
I called Ellen to ask him to call me as I was getting extremely upset with the situation. He didn't call so I sent him a text message asking why he was suddenly incommunicado. He replied back that there's something wrong with his phone and that while he can be heard, he can't hear whoever is on the other side of the line.
That happened to me just last week and the person I called still picked up the phone to tell me he can't hear me and to text him instead. Why didn't he do that? He had no answer.
Might I be reading the situation incorrectly? Maybe. But at the moment I feel that he's mad at me for getting mad at him and thus avoiding me. Well, I certainly hope I'm mistaken as this is not exactly professional behavior.
15 October 2010
It's Raining - INSIDE...
Sigh.
They are now starting to install the sinks and toilets, so a couple of days ago, the plumber tried to test everything by turning on the water supply upstairs. Let's just say that water started coming out of the ceiling and the light switches on the wall. According to the workers who witnessed the event, this resulted in large puddles on the ground floor.
Uh, how did this happen? Well, when the house was turned over to us, they did not install the lavoratories as we asked them not to install the tiles. And while Engr. Rommel told me yesterday that they tested the water pressure of the house, I highly doubt it. Otherwise they would have known about the huge pipe leak located in the bowels of the ceiling.
Apparently, when Avida was installing the metal frames in the house, they drilled a hole through the water pipes... Take note that we've just spent a small fortune (in our opinion) fixing the electrical system not to mention that the ceiling, cornices and walls have already been painted.
I'm now worried about the state of the gypsum board ceiling and the lights. Moisture + darkness = MOLD. And what about the recessed light fixtures that are all made of metal? I have visions of rust dancing in my head.
After a "strongly worded" conversation with Engr. Rommel earlier today, he had John, the contractor, come over to take another look. He also advised that if anything gets damaged then the contractor will pay for it.
Turns out John had been in charge of the house from the beginning. I then took that as a great opportunity to rant about how much cement has been consumed just to fix the very uneven walls and floors! (Sorry, I couldn't help myself considering we paid for the repairs.)
Maricel told me that this happened because Avida sub-contracts the work to others. But I told her that ultimately Avida carries the responsibility of checking the quality of work done. Because in the end, had the house been the picture of perfection, they're going to say that it's Avida who made the house and not JJM (the name of the sub-contracting company).
Is there a solution in the offing? Yes, tomorrow John will be back to check for damages and will replace the areas affected by the water leak at least to start with. I feel bad though because they will probably ruin the work already done by Rabacon.
But if I were to look on the bright side, at least we found this out prior to living in the house and that they will actually fix this mess. Well, they should!
22 July 2010
Short Circuit
As mentioned in the previous post, Electrical Shortage, the house cannot the support the electrical appliances we plan to install. Here's what Avida provided as copied from the panel board schedule located in the building plan:
Here's the computation made by Alecto General Technology Corporation based on what we actually need:
And here's the series of emails triggered by this discrepancy:
From: Nicole
Date: 2010/7/12
To: AVIDA Frolan, AVIDA Ellen
Hi Frolan & Ellen,
Please refer to the email below. According to people from Alecto, the house cannot accommodate the appliances we are planning to plug in:
1.) Water heater for the shower only (x2) - 3kW to 8kW (see website)
2.) Fridge - Whirlpool 21.8 cubic feet - 24 A / 615 W
3.) Washing machine - Whirlpool 10.5 K load - 5 A / 60 HZ
4.) Clothes dryer - Whirlpool 6 K load - 10 A
5.) ACU - split type 2HP - ground floor
6.) ACU - window type 0.75 HP - masters bedroom and the second largest bedroom
They also advised that if we are planning to add more electrical devices in the future (i.e. electrical pump), this will no longer be possible.
We would also like to know why there is only one electrical outlet in each bedroom and why is it located beside the door? Did the planners of Avida not account for what people use in their homes? ACU, night lamps, computers, printers, scanners, TVs, DVD players, etc?
--------------------
From: AVIDA Ellen T.
Date: Tue, Jul 20, 2010 at 5:56 PM
To: Nicole
Hi Ms. Nicole,
Thanks for the advice. With regard to your concerns, the Technical team would like to confirm that indeed the electrical design and load schedules presented in our plans are the standard offering of Avida and in accordance with the Electrical Code. Any upgrade or increase on load requirements outside our specifications shall be on the account of the buyer since electrical design/load schedules are patterned after our standard specs.
Further, the location of our electrical outlets, are based on the suggested floor plans designed by the team (as per brochure inserts).
Also, as verified on site, the rectification of your unit is currently on-going. Will keep you posted until punch lists are fully addressed. Kindly refer to the below update.
-------------------
From: Nicole
Date: Tue, Jul 20, 2010 at 6:40 PM
To: AVIDA Ellen, AVIDA Ruth
Hi Ellen,
Then we have a problem. Had we known that we would not have bought the house but your sales agent assured us that the appliances we planned to install are all possible. Take note that these are just the usual appliances that one buys for a house.
Also, why is the electrical load provided for the ref only 500W? According to Alecto, that's only good for a personal ref.
What kind of house only provides for a personal ref and basically nothing else?
What kind of house only has one electrical outlet per room and it's located by the door of all places? What do you do with the night lamp? Position it by the door?
This is NOT a quality home. Quality does not mean you have to spend extra just so that you can install a fridge. This is UTTERLY RIDICULOUS!!!!!
Also, what brochure inserts? Are they the ones given out to potential customers? Because trust me, it's not indicated there.
If we were to base it on your model unit, each room would have an outlet for the aircon.
Avida is very deceiving. It sells based on lies - A LOT of them.
I called up our sales agent Mich last night and told him to NEVER tell the customers that they can plug in basic appliances. I've also told him that he should also tell them that the waiting time for a house is over a year and that it will be subject to A LOT of repairs once done.
By the way, turnover means that it's ready for move-in. It's mid July and the house is still being repaired. So basically the house is not ready and is now 11 months LATE and counting.
--------------------
From: AVIDA Ellen
Date: Wed, Jul 21, 2010 at 6:19 PM
To: Nicole
Cc: AVIDA Christine
Hi Ms. Nicole,
You may introduce changes, improvements and/or upgrade in your unit but that is through the account of the buyer since your requirements are not within our specifications.
We have delivered a Patrice Standard unit to you as per commitment and disclosed specifications in our plans.
We’ve provided the options (such as Basic, Standard and Premium units) to cater to our buyers need.
Also, model units (both with I.D & non-I.D) were showcased on site to provide buyers better appreciation/ idea of the actual unit they purchase.
Pardon us if the specs on the Standard unit you purchased don’t meet your requirements, but it is our standard deliverable and is in conformance with the house building plan we have provided to our buyers.
--------------------
From: Nicole
Date: Wed, Jul 21, 2010 at 9:45 PM
To: "AVIDA Ellen, AVIDA Ruth
Yes but we were NEVER informed of what the actual electrical capacity was. We were just told it's ALL possible.
THE MODEL UNITS ALL HAVE EXTRA PLUGS - ISN'T THAT DECEIVING?!?!?!
You guys would not even give any of the plans in advance when we asked for it. You gave it after we paid for the house.
Your commitment is whatever your sales agents tell us is possible - especially since the specs given to us don't include anything about the electrical.
So I would suggest that you stop telling us that we knew in advance what came with the house because all we know is what the sales agent told us.
And as to delivering "a Patrice Standard unit to you as per commitment and disclosed specifications in our plans" - are misaligned walls and floors part of your specifications?
THE PROBLEM IS THAT YOU KEEP MAKING PROMISES AND BREAKING ALL OF THEM.
"Pardon us if the specs on the Standard unit you purchased don’t meet your requirements"
YOU'VE GOT TO BE KIDDING!!!!! THIS IS THE BIGGEST MISTAKE WE'VE EVER MADE AND NOT TO MENTION THE MOST EXPENSIVE ONE.
Oh, and the non-ID model unit - it had no walls. THERE WAS NEVER A NON-ID STANDARD MODEL UNIT FOR PATRICE. Don't you guys know that?
SO YOU SHOULD STOP WRITING AS THOUGH WE WERE AWARE OF EVERYTHING THAT CAME WITH THE HOUSE PRIOR TO PAYING FOR IT.
--------------------
I just received the quotation from Alecto on how much it would cost to add extra load and the outlets and their fee will be around Php 160,000. Now that is a little too rich for our blood but the facilities manager at work advised that of all the big name electrical engineering companies he has dealt with, only Alecto has not failed. So by my estimate, other not so well known companies will at least charge Php 100,000.
*Update: Alecto sent another quotation the following day. This time the total cost is Php 121,000. While the new price is better, it's still over Php 100,000.
Earl and I have a bit of money saved up but we were planning to use that for the contractor, the kitchen and if there's anything left over, maybe furniture. We were not planning to spend it on something that should have been provided for to begin with.
I also spoke with Ellen earlier today - despite the emails, I like to think that we're starting to get along. But I pointed out to her that before she sends out an email template, she should try to put herself in our shoes. We've just paid a lot of money for a dud.
I know of others who bought much larger houses at less than what we paid - with complete electrical load and sockets. Can someone remind me again why we decided to go with Avida? I'm starting to forget.
Ellen wants to set up a meeting with us and Noel (her boss). I asked her what good will that do? She said that Noel can make decisions regarding our house. If that's the case, why can't he make a decision now? But I agreed provided that the meeting will be on a Saturday and we can meet at the house.
This entire situation is extremely depressing and I don't think Avida understands the gravity of what their actions have done (starting from the sales agent) and what it is causing us - both mentally and financially.
Here's the computation made by Alecto General Technology Corporation based on what we actually need:
And here's the series of emails triggered by this discrepancy:
From: Nicole
Date: 2010/7/12
To: AVIDA Frolan, AVIDA Ellen
Hi Frolan & Ellen,
Please refer to the email below. According to people from Alecto, the house cannot accommodate the appliances we are planning to plug in:
1.) Water heater for the shower only (x2) - 3kW to 8kW (see website)
2.) Fridge - Whirlpool 21.8 cubic feet - 24 A / 615 W
3.) Washing machine - Whirlpool 10.5 K load - 5 A / 60 HZ
4.) Clothes dryer - Whirlpool 6 K load - 10 A
5.) ACU - split type 2HP - ground floor
6.) ACU - window type 0.75 HP - masters bedroom and the second largest bedroom
They also advised that if we are planning to add more electrical devices in the future (i.e. electrical pump), this will no longer be possible.
We would also like to know why there is only one electrical outlet in each bedroom and why is it located beside the door? Did the planners of Avida not account for what people use in their homes? ACU, night lamps, computers, printers, scanners, TVs, DVD players, etc?
--------------------
From: AVIDA Ellen T.
Date: Tue, Jul 20, 2010 at 5:56 PM
To: Nicole
Hi Ms. Nicole,
Thanks for the advice. With regard to your concerns, the Technical team would like to confirm that indeed the electrical design and load schedules presented in our plans are the standard offering of Avida and in accordance with the Electrical Code. Any upgrade or increase on load requirements outside our specifications shall be on the account of the buyer since electrical design/load schedules are patterned after our standard specs.
Further, the location of our electrical outlets, are based on the suggested floor plans designed by the team (as per brochure inserts).
Also, as verified on site, the rectification of your unit is currently on-going. Will keep you posted until punch lists are fully addressed. Kindly refer to the below update.
-------------------
From: Nicole
Date: Tue, Jul 20, 2010 at 6:40 PM
To: AVIDA Ellen, AVIDA Ruth
Hi Ellen,
Then we have a problem. Had we known that we would not have bought the house but your sales agent assured us that the appliances we planned to install are all possible. Take note that these are just the usual appliances that one buys for a house.
Also, why is the electrical load provided for the ref only 500W? According to Alecto, that's only good for a personal ref.
What kind of house only provides for a personal ref and basically nothing else?
What kind of house only has one electrical outlet per room and it's located by the door of all places? What do you do with the night lamp? Position it by the door?
This is NOT a quality home. Quality does not mean you have to spend extra just so that you can install a fridge. This is UTTERLY RIDICULOUS!!!!!
Also, what brochure inserts? Are they the ones given out to potential customers? Because trust me, it's not indicated there.
If we were to base it on your model unit, each room would have an outlet for the aircon.
Avida is very deceiving. It sells based on lies - A LOT of them.
I called up our sales agent Mich last night and told him to NEVER tell the customers that they can plug in basic appliances. I've also told him that he should also tell them that the waiting time for a house is over a year and that it will be subject to A LOT of repairs once done.
By the way, turnover means that it's ready for move-in. It's mid July and the house is still being repaired. So basically the house is not ready and is now 11 months LATE and counting.
--------------------
From: AVIDA Ellen
Date: Wed, Jul 21, 2010 at 6:19 PM
To: Nicole
Cc: AVIDA Christine
Hi Ms. Nicole,
You may introduce changes, improvements and/or upgrade in your unit but that is through the account of the buyer since your requirements are not within our specifications.
We have delivered a Patrice Standard unit to you as per commitment and disclosed specifications in our plans.
We’ve provided the options (such as Basic, Standard and Premium units) to cater to our buyers need.
Also, model units (both with I.D & non-I.D) were showcased on site to provide buyers better appreciation/ idea of the actual unit they purchase.
Pardon us if the specs on the Standard unit you purchased don’t meet your requirements, but it is our standard deliverable and is in conformance with the house building plan we have provided to our buyers.
--------------------
From: Nicole
Date: Wed, Jul 21, 2010 at 9:45 PM
To: "AVIDA Ellen, AVIDA Ruth
Yes but we were NEVER informed of what the actual electrical capacity was. We were just told it's ALL possible.
THE MODEL UNITS ALL HAVE EXTRA PLUGS - ISN'T THAT DECEIVING?!?!?!
You guys would not even give any of the plans in advance when we asked for it. You gave it after we paid for the house.
Your commitment is whatever your sales agents tell us is possible - especially since the specs given to us don't include anything about the electrical.
So I would suggest that you stop telling us that we knew in advance what came with the house because all we know is what the sales agent told us.
And as to delivering "a Patrice Standard unit to you as per commitment and disclosed specifications in our plans" - are misaligned walls and floors part of your specifications?
THE PROBLEM IS THAT YOU KEEP MAKING PROMISES AND BREAKING ALL OF THEM.
"Pardon us if the specs on the Standard unit you purchased don’t meet your requirements"
YOU'VE GOT TO BE KIDDING!!!!! THIS IS THE BIGGEST MISTAKE WE'VE EVER MADE AND NOT TO MENTION THE MOST EXPENSIVE ONE.
Oh, and the non-ID model unit - it had no walls. THERE WAS NEVER A NON-ID STANDARD MODEL UNIT FOR PATRICE. Don't you guys know that?
SO YOU SHOULD STOP WRITING AS THOUGH WE WERE AWARE OF EVERYTHING THAT CAME WITH THE HOUSE PRIOR TO PAYING FOR IT.
--------------------
I just received the quotation from Alecto on how much it would cost to add extra load and the outlets and their fee will be around Php 160,000. Now that is a little too rich for our blood but the facilities manager at work advised that of all the big name electrical engineering companies he has dealt with, only Alecto has not failed. So by my estimate, other not so well known companies will at least charge Php 100,000.
*Update: Alecto sent another quotation the following day. This time the total cost is Php 121,000. While the new price is better, it's still over Php 100,000.
Earl and I have a bit of money saved up but we were planning to use that for the contractor, the kitchen and if there's anything left over, maybe furniture. We were not planning to spend it on something that should have been provided for to begin with.
I also spoke with Ellen earlier today - despite the emails, I like to think that we're starting to get along. But I pointed out to her that before she sends out an email template, she should try to put herself in our shoes. We've just paid a lot of money for a dud.
I know of others who bought much larger houses at less than what we paid - with complete electrical load and sockets. Can someone remind me again why we decided to go with Avida? I'm starting to forget.
Ellen wants to set up a meeting with us and Noel (her boss). I asked her what good will that do? She said that Noel can make decisions regarding our house. If that's the case, why can't he make a decision now? But I agreed provided that the meeting will be on a Saturday and we can meet at the house.
This entire situation is extremely depressing and I don't think Avida understands the gravity of what their actions have done (starting from the sales agent) and what it is causing us - both mentally and financially.
21 July 2010
Electrical Shortage
Literally.
It all started with the need for additional electrical outlets.
The circles above mark the location of the electrical outlets on the second floor. Notice that the two other bedrooms have just one outlet which is located beside the door.
But before anything else, let me start from the beginning.
When we were talking to our sales agent, we asked him if the appliances we were planning to install (i.e. washing machine, dryer, water heaters for the two showers, side by side fridge, etc.) would be possible with the electrical load of the house. He said yes.
Now that the house has been turned over to us, we've discovered that there is only one electrical outlet in the other two bedrooms. Where do we plug the night lamps, computer, printer, air conditioner, etc? Are we supposed to stretch the cords across the room to where the door is?
But as it turns out, that's the least of our problems.
Initially, we inquired with Alecto General Technology Corporation (an electrical engineering company recommend by the facilities manager at work) how much it would cost to install additional outlets.
They asked for a copy of the Avida electrical plan, pictures of the panel board and a detailed list of the appliances we're planning to install:
1.) Water heater for the shower only (x2) - 3kW to 8kW (Alpha-LH-1000E)
2.) Fridge - Whirlpool 21.8 cubic feet - 24 A / 615 W
3.) Washing machine - Whirlpool 10.5 K load - 5 A / 60 HZ
4.) Clothes dryer - Whirlpool 6 K load - 10 A
5.) ACU - split type 2HP - ground floor
6.) ACU - window type 0.75 HP - masters bedroom and the second largest bedroom
After studying the Avida electrical plan, Alecto advised that the load of the house is only 60.6 amps (line current at 100% Demand Factor), while what we need for the electrical devices mentioned above is 95.34 amps (line current at 80% Demand Factor).
They also said that the electrical load for the fridge provided by Avida is 543W which is essentially good for just a PERSONAL REFRIGERATOR. The fridge we plan to install needs 5520W.
Basically, the house is SHORT by 34.74 amps. And if we plan to install a water pump with an electrical booster (or anything else for that matter) in the future, it will no longer be possible.
Avida's response to all this is that they can only provide what's in the plan and anything outside of that will be for us to install. They also told me that the neighbors have installed all sorts of things including electrical fences and there doesn't seem to be a problem.
To this Alecto explained that house fires are caused not by faulty wiring, but due to misuse of the owner. They explained that not all outlets are created equal (meaning you just can't plug in anything you like). And based on the breakdown given by Avida for the outlets, what Alecto is saying is true as each outlet has a specific capacity.
Just last week, Ellen from Avida was assuring me (yet again) that we will get a quality house. What kind of quality are they talking about if, to install basic appliances, we need to shell out a ton of money (minimum Php 80,000 according to Alecto) just so that we can actually plug in those devices and ensure we won't have an electrical shortage?
I have come to the conclusion that if you wish to purchase from Avida, just buy the lot and build the house yourselves. Because the house that Avida provides is not the kind where once finished, you can move in already. You will need to add and spend for many things just so that you can live in it.
It all started with the need for additional electrical outlets.
Second Level Power and Auxiliary Layout
But before anything else, let me start from the beginning.
When we were talking to our sales agent, we asked him if the appliances we were planning to install (i.e. washing machine, dryer, water heaters for the two showers, side by side fridge, etc.) would be possible with the electrical load of the house. He said yes.
Now that the house has been turned over to us, we've discovered that there is only one electrical outlet in the other two bedrooms. Where do we plug the night lamps, computer, printer, air conditioner, etc? Are we supposed to stretch the cords across the room to where the door is?
But as it turns out, that's the least of our problems.
Initially, we inquired with Alecto General Technology Corporation (an electrical engineering company recommend by the facilities manager at work) how much it would cost to install additional outlets.
They asked for a copy of the Avida electrical plan, pictures of the panel board and a detailed list of the appliances we're planning to install:
1.) Water heater for the shower only (x2) - 3kW to 8kW (Alpha-LH-1000E)
2.) Fridge - Whirlpool 21.8 cubic feet - 24 A / 615 W
3.) Washing machine - Whirlpool 10.5 K load - 5 A / 60 HZ
4.) Clothes dryer - Whirlpool 6 K load - 10 A
5.) ACU - split type 2HP - ground floor
6.) ACU - window type 0.75 HP - masters bedroom and the second largest bedroom
After studying the Avida electrical plan, Alecto advised that the load of the house is only 60.6 amps (line current at 100% Demand Factor), while what we need for the electrical devices mentioned above is 95.34 amps (line current at 80% Demand Factor).
They also said that the electrical load for the fridge provided by Avida is 543W which is essentially good for just a PERSONAL REFRIGERATOR. The fridge we plan to install needs 5520W.
Basically, the house is SHORT by 34.74 amps. And if we plan to install a water pump with an electrical booster (or anything else for that matter) in the future, it will no longer be possible.
Avida's response to all this is that they can only provide what's in the plan and anything outside of that will be for us to install. They also told me that the neighbors have installed all sorts of things including electrical fences and there doesn't seem to be a problem.
To this Alecto explained that house fires are caused not by faulty wiring, but due to misuse of the owner. They explained that not all outlets are created equal (meaning you just can't plug in anything you like). And based on the breakdown given by Avida for the outlets, what Alecto is saying is true as each outlet has a specific capacity.
Just last week, Ellen from Avida was assuring me (yet again) that we will get a quality house. What kind of quality are they talking about if, to install basic appliances, we need to shell out a ton of money (minimum Php 80,000 according to Alecto) just so that we can actually plug in those devices and ensure we won't have an electrical shortage?
I have come to the conclusion that if you wish to purchase from Avida, just buy the lot and build the house yourselves. Because the house that Avida provides is not the kind where once finished, you can move in already. You will need to add and spend for many things just so that you can live in it.
30 June 2010
Have Keys, Need Furniture...
And tiles, paint, stove, fridge, microwave, shelves, closets, and everything else in between.
It has been four days since the house was turned over to us by Desiree from Avida. Earl and I brought along Architect Mario (aka Uncle Mayong) to go over the place with Engineers Frolan (who is also an Avida Property Manager) and Mark.
But we cannot move in just yet and work on the house as there are many items that still need fixing:
- uneven walls
- uneven floors
- exposed pipes both inside and outside the house
- unfinished surfaces
- even more holes in the walls that need to be sealed
- water coming in through the back door when it rains
- concrete front porch area is hollow underneath
With regards to the uneven floor, Engr. Frolan advised that things will even themselves out when we have our flooring material installed (i.e. laminated wood). Somehow though that didn't sound quite right... I said to him that we should not be fixing the mistakes made by Avida and that quality does not mean "repairs needed". I also told Uncle Mayong about it and he definitely agreed with me.
Sigh (again). Truth be told, I am not too upset about the situation probably because I anticipated this happening. And when you expect it, then it's not a surprise. Well, at least the house is a beautiful shade of blue!
So, I've now decided to concentrate on the next phase - fixing up the house. And to say that I am excited about this is a HUGE understatement!
27 June 2010
The Legal Department: Rebuttal & Closing Arguments
Our Rebuttal dated May 28:
This is in response to your letter of reply dated “May 17, 2009” (sic), apologizing for the delay in turning over the property of my clients, Spouses Earl and Nicole... In the same letter, you mentioned that you have granted certain concessions to my client for the delay and thus should be evidence that the award of damages is unwarranted.
Please allow us to argue why these concessions were inadequate to compensate for the inconveniences.
In item #1, the granting of my clients’ request to delay the release of the proceeds of the loan from PSBank, the bank selected by my clients, cannot be deemed as a concession because, as per policy, the bank cannot release the loan amount until the unit is 100% complete. This was not a condition set by my clients. Avida should know this because it accredited the said bank.
As to item #2, it should have been an easy task for Avida to extend and shoulder the replacement fees for the EGC as it was issued by Ayala Malls, which has the same ownership as Avida. In addition, there have been four promised delivery dates – August 2009 (by the sales agent), fourth quarter 2009 (according to the contract), 31 March 2010 (by Ruth G. from Avida Land), and 30 April 2010 (by Ellen S. from Avida Land). My clients do not find it acceptable that there have been four promised delivery dates, none of which were met.
Regarding item #3, the Property being painted “blue” cannot be deemed as a concession. In Annex C and Annex C-1 of the contract, the color of the house has been specified as “blue”. Painting the property a color other than “blue” would have been a breach of contract once again.
We also sent them a formal letter of complaint (the contents of which have been mentioned in previous blog posts that you can read here and here).
Avida's Closing Arguments dated June 9:
Regarding the rectifications requested by your clients on the Unit, please be informed of the following:
1. Avida has already corrected the typographical error in the technical description of the Unit;
2. Completed the repainting of the exterior wall of the Unit with your clients' preferred color (blue);
3. Doors were already adjusted and holes were fixed;
4. Ground floor Toilet & Bath (T & B) - part of the walls on this T & B were not painted since the unpainted portion of said walls is where the preferred tiles of our client will also be installed, in addition to the floor tiles. Your client requested not to install the standard tiles used by Avida for this particular house model.
In your letter, we understand that you have advised your clients to settle this case for a compensation of rentals paid... on the house leased by Spouses pending the turn-over, plus payment of attorney’s fees.
We wish to emphasize that pursuant to the Contract to Sell executed between Avida and your clients, the stated turn-over date of the Unit is last quarter of calendar year 2009. Thus, legally and based on the express provisions of the Contract to Sell, Avida has until the end of December 2009 to turn-over the Unit. In other words, Avida only incurred delay in the turn-over of the Unit beginning January 2010. However; in the interest of fair settlement of this matter, Avida shall shoulder the rental beginning December 2009 until May 2010, ...notwithstanding that delay by Avida has not yet occurred as of December 2009. This amount is the final offer of Avida and shall be effective only until June 18, 2010.
TURN-OVER OF UNIT / RELEASE OF LOAN PROCEEDS
Avida is ready to turn over the unit to your clients by June 18, 2010 subject to the release of the PSBank loan proceeds to pay the purchase price of the Unit. In this regard, Avida respectfully requests that your clients instruct and arrange with PSBank for release of the loan proceeds on June 15, 2010. Please note the release of the loan proceeds is a non-negotiable condition precedent of Avida for the formal turn-over of the Unit. Avida has already complied with all the constructions requests of your client concerning the Unit.
If your client is not able to process and facilitate the release of the loan proceeds by June 15, 2010, Avida shall be constrained, much to our regret, to cancel the Contract to Sell over the Unit for non-performance / breach of your clients’ obligation to pay the purchase price of the Unit.
Uh, Avida, you can't demand a time limit if you yourself can't follow your own deadlines... Just a thought.
In our complaint letter, we never mentioned the color of the house as it was already painted blue as of April 30 (a month ago). It's either you can't keep your facts straight or you're trying to pad your list of "good deeds."
I could argue some more but we are tired. This whole situation has brought about a lot of conflict and ill will - so much so that at one point we actually considered giving up the house. We now just want this to end as quickly as possible so that we can move on to better things - like planning how to decorate!
Sigh. Avida, do you know that all this could have been avoided?
__________
Note: I have only included sections of the letter which I think are important and have omitted those which I have deemed irrelevant to this post.
This is in response to your letter of reply dated “May 17, 2009” (sic), apologizing for the delay in turning over the property of my clients, Spouses Earl and Nicole... In the same letter, you mentioned that you have granted certain concessions to my client for the delay and thus should be evidence that the award of damages is unwarranted.
Please allow us to argue why these concessions were inadequate to compensate for the inconveniences.
In item #1, the granting of my clients’ request to delay the release of the proceeds of the loan from PSBank, the bank selected by my clients, cannot be deemed as a concession because, as per policy, the bank cannot release the loan amount until the unit is 100% complete. This was not a condition set by my clients. Avida should know this because it accredited the said bank.
As to item #2, it should have been an easy task for Avida to extend and shoulder the replacement fees for the EGC as it was issued by Ayala Malls, which has the same ownership as Avida. In addition, there have been four promised delivery dates – August 2009 (by the sales agent), fourth quarter 2009 (according to the contract), 31 March 2010 (by Ruth G. from Avida Land), and 30 April 2010 (by Ellen S. from Avida Land). My clients do not find it acceptable that there have been four promised delivery dates, none of which were met.
Regarding item #3, the Property being painted “blue” cannot be deemed as a concession. In Annex C and Annex C-1 of the contract, the color of the house has been specified as “blue”. Painting the property a color other than “blue” would have been a breach of contract once again.
We also sent them a formal letter of complaint (the contents of which have been mentioned in previous blog posts that you can read here and here).
Avida's Closing Arguments dated June 9:
Regarding the rectifications requested by your clients on the Unit, please be informed of the following:
1. Avida has already corrected the typographical error in the technical description of the Unit;
2. Completed the repainting of the exterior wall of the Unit with your clients' preferred color (blue);
3. Doors were already adjusted and holes were fixed;
4. Ground floor Toilet & Bath (T & B) - part of the walls on this T & B were not painted since the unpainted portion of said walls is where the preferred tiles of our client will also be installed, in addition to the floor tiles. Your client requested not to install the standard tiles used by Avida for this particular house model.
In your letter, we understand that you have advised your clients to settle this case for a compensation of rentals paid... on the house leased by Spouses pending the turn-over, plus payment of attorney’s fees.
We wish to emphasize that pursuant to the Contract to Sell executed between Avida and your clients, the stated turn-over date of the Unit is last quarter of calendar year 2009. Thus, legally and based on the express provisions of the Contract to Sell, Avida has until the end of December 2009 to turn-over the Unit. In other words, Avida only incurred delay in the turn-over of the Unit beginning January 2010. However; in the interest of fair settlement of this matter, Avida shall shoulder the rental beginning December 2009 until May 2010, ...notwithstanding that delay by Avida has not yet occurred as of December 2009. This amount is the final offer of Avida and shall be effective only until June 18, 2010.
TURN-OVER OF UNIT / RELEASE OF LOAN PROCEEDS
Avida is ready to turn over the unit to your clients by June 18, 2010 subject to the release of the PSBank loan proceeds to pay the purchase price of the Unit. In this regard, Avida respectfully requests that your clients instruct and arrange with PSBank for release of the loan proceeds on June 15, 2010. Please note the release of the loan proceeds is a non-negotiable condition precedent of Avida for the formal turn-over of the Unit. Avida has already complied with all the constructions requests of your client concerning the Unit.
If your client is not able to process and facilitate the release of the loan proceeds by June 15, 2010, Avida shall be constrained, much to our regret, to cancel the Contract to Sell over the Unit for non-performance / breach of your clients’ obligation to pay the purchase price of the Unit.
Uh, Avida, you can't demand a time limit if you yourself can't follow your own deadlines... Just a thought.
In our complaint letter, we never mentioned the color of the house as it was already painted blue as of April 30 (a month ago). It's either you can't keep your facts straight or you're trying to pad your list of "good deeds."
I could argue some more but we are tired. This whole situation has brought about a lot of conflict and ill will - so much so that at one point we actually considered giving up the house. We now just want this to end as quickly as possible so that we can move on to better things - like planning how to decorate!
Sigh. Avida, do you know that all this could have been avoided?
__________
Note: I have only included sections of the letter which I think are important and have omitted those which I have deemed irrelevant to this post.
25 June 2010
The Legal Department: Opening Statements
As mentioned in a previous post (you can read it here), due to the trouble we were having with Avida, our lawyer sent a demand letter for breach of contract. Here's what Atty. Stephen sent:
I write in behalf of Sps Earl and Nicole. You have executed a Contract to Sell, whereby you promised to deliver a house and lot... start of last quarter of 2009, i.e. Oct. 1, 2009 to said Spouses.
You have grossly defaulted on such promise, even while your agents promised earlier date of completion of August 2009.
While the Spouses expected to transfer residence on Oct 1, 2009, to save on monthly rentals they were paying at their residence..., they were disgusted that for no justifiable reason you were not able to deliver but that thru email your agents promised a delayed completion date of March 31, 2010. Again what a frustration for them to find out that the house was not finished by March 31, 2010, and again your agents promised end of April, with apologies.
The Spouses cannot take it anymore. You have to compensate their damage consisting of 7 months rentals, besides their moral and exemplary damages for your wanton breach of the contract, ...plus Atty’s Fees.
Avida's reply dated May 17:
Please allow us to extend our sincerest apologies to your clients, Spouses Earl and Nicole, for the unintentional delay in the turnover of the Property and to accept Avida's heartfelt apologies for any inconvenience this may have caused your clients. We wish to inform you that Avida has addressed the cause of this delay and is now ready to turn-over the Property to the Spouses, subject only to the release of the bank loan proceeds applied for by your clients as payment for the Property.
As a brief background, the delay in the original turn-over date of end of the calendar year 2009 was earlier communicated to the Spouses in January 2010. To compensate for this unintentional delay, Avida consented to your client's request to hold off of likewise delay the release of the proceeds of the bank loan secured by the Spouses, until such time when the Property is ready to be turned over to your clients. The loan proceeds would have served as the payment by your clients for the Property purchased from Avida. In addition, Avida also consented to the extension of the availment of the EGC sales promotion. The EGC sales promotion was an add-on incentive given to buyers that should only be used within the validity period but Avida allowed the extension and shouldered the replacement fees.
We do understand that several communications between Avida and the Spouses have transpired to another extension of the turn over date to April 30, 2010. Rest assured that Avida has addressed the internal issues which caused the delay and is now ready to turn over the Property to the Spouses, subject to the release of the bank loan proceeds for the payment of the purchase price of the Property. Please note also that as per your client's request, the Property has been painted "blue".
Will all due respect and as evidenced by the aforementioned concessions granted by Avida to the Spouses for the unintentional delay in the turn over of the Property, Avida firmly believes that it did not act in bad faith, in a wanton, fraudulent, reckless, oppressive or malevolent manner as to warrant the award of damages as claimed by your clients.
The first paragraphs felt sincere but the rest of it gave me an apoplectic fit - thus negating any happy thoughts I might have had while reading the first few lines.
Avida, you make it sound as if you had been giving us constant updates. And may I please ask how much did you pay for the fees? Did the amount reach into the thousands? Somehow, I highly doubt it. Also, I didn't know you could delay the release of the loan - you just gave me an idea (thanks!)... Oh, and that fourth paragraph - a bit of an overkill.
But I have noticed that Avida does try, really they do - I will say that for them. They come off great at the start but have trouble coming through to the end and their response letter is an example of that. You could say their heart is in the right place, they just need to work on the follow through - which in my opinion is the most important part.
__________
Note: I have only included sections of the letter which I think are important and have omitted those which I have deemed irrelevant to this post.
I write in behalf of Sps Earl and Nicole. You have executed a Contract to Sell, whereby you promised to deliver a house and lot... start of last quarter of 2009, i.e. Oct. 1, 2009 to said Spouses.
You have grossly defaulted on such promise, even while your agents promised earlier date of completion of August 2009.
While the Spouses expected to transfer residence on Oct 1, 2009, to save on monthly rentals they were paying at their residence..., they were disgusted that for no justifiable reason you were not able to deliver but that thru email your agents promised a delayed completion date of March 31, 2010. Again what a frustration for them to find out that the house was not finished by March 31, 2010, and again your agents promised end of April, with apologies.
The Spouses cannot take it anymore. You have to compensate their damage consisting of 7 months rentals, besides their moral and exemplary damages for your wanton breach of the contract, ...plus Atty’s Fees.
Avida's reply dated May 17:
Please allow us to extend our sincerest apologies to your clients, Spouses Earl and Nicole, for the unintentional delay in the turnover of the Property and to accept Avida's heartfelt apologies for any inconvenience this may have caused your clients. We wish to inform you that Avida has addressed the cause of this delay and is now ready to turn-over the Property to the Spouses, subject only to the release of the bank loan proceeds applied for by your clients as payment for the Property.
As a brief background, the delay in the original turn-over date of end of the calendar year 2009 was earlier communicated to the Spouses in January 2010. To compensate for this unintentional delay, Avida consented to your client's request to hold off of likewise delay the release of the proceeds of the bank loan secured by the Spouses, until such time when the Property is ready to be turned over to your clients. The loan proceeds would have served as the payment by your clients for the Property purchased from Avida. In addition, Avida also consented to the extension of the availment of the EGC sales promotion. The EGC sales promotion was an add-on incentive given to buyers that should only be used within the validity period but Avida allowed the extension and shouldered the replacement fees.
We do understand that several communications between Avida and the Spouses have transpired to another extension of the turn over date to April 30, 2010. Rest assured that Avida has addressed the internal issues which caused the delay and is now ready to turn over the Property to the Spouses, subject to the release of the bank loan proceeds for the payment of the purchase price of the Property. Please note also that as per your client's request, the Property has been painted "blue".
Will all due respect and as evidenced by the aforementioned concessions granted by Avida to the Spouses for the unintentional delay in the turn over of the Property, Avida firmly believes that it did not act in bad faith, in a wanton, fraudulent, reckless, oppressive or malevolent manner as to warrant the award of damages as claimed by your clients.
The first paragraphs felt sincere but the rest of it gave me an apoplectic fit - thus negating any happy thoughts I might have had while reading the first few lines.
Avida, you make it sound as if you had been giving us constant updates. And may I please ask how much did you pay for the fees? Did the amount reach into the thousands? Somehow, I highly doubt it. Also, I didn't know you could delay the release of the loan - you just gave me an idea (thanks!)... Oh, and that fourth paragraph - a bit of an overkill.
But I have noticed that Avida does try, really they do - I will say that for them. They come off great at the start but have trouble coming through to the end and their response letter is an example of that. You could say their heart is in the right place, they just need to work on the follow through - which in my opinion is the most important part.
__________
Note: I have only included sections of the letter which I think are important and have omitted those which I have deemed irrelevant to this post.
21 June 2010
Miscellaneous Information
TCT – Donna from the Avida Land Inc. (ALI) Group Support sent us an email last June 6 that the Transfer Certificate of Title (TCT) error has been corrected. She also advised that their sales documentation team will send an update once they have reviewed the documents.
As of today, they have yet to send the corrected forms for our signature. Actually, we have not heard from them since.
House Turnover – In a letter dated June 9, Avida advised that our new turnover date is scheduled for June 18. Since they gave the notification more than a week in advance, is it too much to hope that they are going to thoroughly check the house this time? We’re crossing our fingers...
Bank Loan – Christine from the bank informed me today that the loan proceeds have been released to Avida last June 16. This means our amortization will start next month, July 16.
We are now heavily mortgaged and actually quite happy about it - at least at the moment.
As of today, they have yet to send the corrected forms for our signature. Actually, we have not heard from them since.
House Turnover – In a letter dated June 9, Avida advised that our new turnover date is scheduled for June 18. Since they gave the notification more than a week in advance, is it too much to hope that they are going to thoroughly check the house this time? We’re crossing our fingers...
Bank Loan – Christine from the bank informed me today that the loan proceeds have been released to Avida last June 16. This means our amortization will start next month, July 16.
We are now heavily mortgaged and actually quite happy about it - at least at the moment.
30 May 2010
The Devil is in the Details
Last May 18, we received a bunch of documents from Avida requiring our signature. I assumed this was part of the turnover process since they sent photocopies of the Transfer Certificate of Title (TCT) and asked us to sign each copy.
I checked the lot plan versus the technical description stated on the TCT and found an error. Since the documents came with a letter that stated a number to call and an email address in case we had questions, I decided to contact them.
To cut things short, after numerous phone calls and emails, Avida has yet to give us an answer more than a week later.
At the same time, I was also communicating with the bank. They told me that typographical errors are common in TCTs but they will try to get some form of guarantee from Avida that they will fix the problem.
I told both the bank and Avida that we will not sign anything until this issue is resolved. And while I know this is a minor detail, we just don't want to be stuck holding the bag (so to speak) if this was overlooked. Apparently, if the actual title has a problem, it could take up to six months and a court hearing - not to mention dealing with different government agencies. Life is difficult enough as it is.
I checked the lot plan versus the technical description stated on the TCT and found an error. Since the documents came with a letter that stated a number to call and an email address in case we had questions, I decided to contact them.
To cut things short, after numerous phone calls and emails, Avida has yet to give us an answer more than a week later.
At the same time, I was also communicating with the bank. They told me that typographical errors are common in TCTs but they will try to get some form of guarantee from Avida that they will fix the problem.
I told both the bank and Avida that we will not sign anything until this issue is resolved. And while I know this is a minor detail, we just don't want to be stuck holding the bag (so to speak) if this was overlooked. Apparently, if the actual title has a problem, it could take up to six months and a court hearing - not to mention dealing with different government agencies. Life is difficult enough as it is.
24 May 2010
The Avida Website Revisted
Brand Promise
Quality Assurance
To ensure the long-term value of your investment, all aspects of our technical planning and construction undergo stringent quality controls. Structural designs are accomplished by highly experienced engineers, while our construction management processes employ an ISO-certified management system.
ISO-certified? With doors that don't open properly? It should be revoked! Hey, there's an idea...
Of course, apart from topnotch quality, Avida is highly committed to the prompt delivery of all projects according to specifications.
Prompt delivery? The number of disgruntled customers that I know of, whose houses were late by at least six months, is growing. And don't get me started on the "according to specifications."
Stress-free Buying Experience
We believe that our customers' buying experience is an integral part of our value proposition. We make sure that site visits are as informative and as relaxing as possible. Our brokers and employees adhere to strict ethical standards, while our dedicated customer hot line is readily available to address all your concerns.
Is it ethical to repeatedly not tell the truth? The head office and the sales agents have yet to learn honesty.
During one site visit, we asked about the bathroom window on the ground floor. Based on the model unit, anyone passing by outside will be able to see the person inside. Our agent assured us that the model unit was done incorrectly and the actual house will not have that problem. Our house now has a problem.
Mission Vision
CUSTOMER SERVICE, QUALITY, COMMITMENT, INTEGRITY and TEAMWORK.
To our Customers, we commit to provide the highest value for your investment by delivering quality and innovative homes and communities that continue to appreciate over time. We will endeavor to build customers for life by providing the highest standards of service and constantly improving quality.
None of the above is happening.
Filinvest, Vista Land and other developers do not make the same detailed claims. At least not on their websites.
Quality Assurance
To ensure the long-term value of your investment, all aspects of our technical planning and construction undergo stringent quality controls. Structural designs are accomplished by highly experienced engineers, while our construction management processes employ an ISO-certified management system.
ISO-certified? With doors that don't open properly? It should be revoked! Hey, there's an idea...
Of course, apart from topnotch quality, Avida is highly committed to the prompt delivery of all projects according to specifications.
Prompt delivery? The number of disgruntled customers that I know of, whose houses were late by at least six months, is growing. And don't get me started on the "according to specifications."
Stress-free Buying Experience
We believe that our customers' buying experience is an integral part of our value proposition. We make sure that site visits are as informative and as relaxing as possible. Our brokers and employees adhere to strict ethical standards, while our dedicated customer hot line is readily available to address all your concerns.
Is it ethical to repeatedly not tell the truth? The head office and the sales agents have yet to learn honesty.
During one site visit, we asked about the bathroom window on the ground floor. Based on the model unit, anyone passing by outside will be able to see the person inside. Our agent assured us that the model unit was done incorrectly and the actual house will not have that problem. Our house now has a problem.
Mission Vision
CUSTOMER SERVICE, QUALITY, COMMITMENT, INTEGRITY and TEAMWORK.
To our Customers, we commit to provide the highest value for your investment by delivering quality and innovative homes and communities that continue to appreciate over time. We will endeavor to build customers for life by providing the highest standards of service and constantly improving quality.
None of the above is happening.
Filinvest, Vista Land and other developers do not make the same detailed claims. At least not on their websites.
23 May 2010
Quality Control Has Left the Building
Either that or it never arrived.
Let's recap. In Ellen's email last March 23 (you can read it here), she advised that, "After the unit has been completed, we will endorse it right away to the Quality team of Avida for quality inspection." She also insisted (while we were arguing on the phone last January) that it will be a quality checked house.
And when I talked to the contractor last month, he confirmed that the Quality team did arrive and inspected the unit. I assumed that what they meant by "quality" was that the house would be conforming to high standards. Apparently, I assumed too much.
We visited the house yesterday and here's what greeted us:
- Doors that won't and can't open fully - take note of the plural form "doors".
- Bathroom walls that have not been paved or painted - the agreement was that they would not install the tiles but the walls would be smooth and painted white.
- Holes due to the doors hitting the walls.
- Toilet bowls, sinks, toilet paper holders, etc that have not been installed - during our meeting with Avida, we agreed that only the tiles would not be installed but everything else stays as is. We also have this in writing.
We would have probably found more defects if we had more time, but I had an event to attend in Makati so we left early.
This now begs the question, WHAT ON EARTH DID THEY CHECK?!?!? And if there are numerous problems for the items that we can immediately see, what more for the things that are out of sight? Like the plumbing and electrical wires?
Avida, we already saved you a lot of money on material and labor costs because of the items we requested not to be installed. But it seems you wanted to save even more money (at our expense) because you have not installed more items than we asked for.
I can now, without a doubt, say we were right in questioning how well this house was built. Quality, huh? Now we know what Avida means by "quality" - it's poor quality. Very poor quality.
20 May 2010
Something is Brewing
Avida sent a letter recently and it made me want to hit someone.
I was so mad that I called Noel three times only to be stopped by Earl. He wants our lawyer to handle this and as much as I really want to start screaming at someone from Avida, I agreed.
The gist is that they have a lot nerve sending that letter. The gall!!!
I will post all the details once I get the go signal.
It may now be time to escalate this situation to someone else.
I was so mad that I called Noel three times only to be stopped by Earl. He wants our lawyer to handle this and as much as I really want to start screaming at someone from Avida, I agreed.
The gist is that they have a lot nerve sending that letter. The gall!!!
I will post all the details once I get the go signal.
It may now be time to escalate this situation to someone else.
07 May 2010
One Final Look Back
When I talked to the contractor last Friday, April 30, he mentioned that the quality control people were at the house Thursday and they gave him some punch list items (still undone). He said he finished them that Friday morning. Basically, this means that the house could not have been turned over that day as per Avida's email (again) since the contractor was still fixing things.
He also mentioned that the house has now been painted blue and that it was finished in half the time it usually takes to paint the house (including primer). In one of our earlier conversations, he said that it would take four days for four men to paint. But since there were 10 men working on the job, it got fixed in a jiffy.
This just proves that it is possible for things to move quickly, provided that Avida puts their mind to it (or you have your lawyer send them a demand letter...)
I wish that Avida had been honest from the beginning. Instead of their sales agents telling potential buyers that they will get their house in six months, they should give the realistic picture and let the clients decide whether or not they want to wait that long BEFORE they hand over the non refundable reservation fee.
Also, during our meeting with Avida last year, we were told that the sales department has a different take on what's supposed to happen which is contrary to the rules set up by the head office. First of all, the sales department and the head office must be in sync with what they tell the customers. As we mentioned to them, the sales people are the first (and sometimes) the only Avida employees that the buyers see - so they all must be on the same page.
But what really got our goat during this process was the fact the "Customer Service" personnel do not tell the truth. They say many things but none of which are true so they end up looking worse than the sales agents they're blaming.
It is our hope that this will not happen again to some other hapless buyer out there, believing the hype and handing over a lot of cash to Avida only to end up frustrated and disappointed. Avida, the houses you sell are not exactly what you call affordable - because if it were then there wouldn't be a housing backlog in this country.
The house is finished but we are not what you can call totally happy or satisfied. And if Avida thinks one bunch of flowers will make up for all the misery they have caused us, think again.
He also mentioned that the house has now been painted blue and that it was finished in half the time it usually takes to paint the house (including primer). In one of our earlier conversations, he said that it would take four days for four men to paint. But since there were 10 men working on the job, it got fixed in a jiffy.
This just proves that it is possible for things to move quickly, provided that Avida puts their mind to it (or you have your lawyer send them a demand letter...)
I wish that Avida had been honest from the beginning. Instead of their sales agents telling potential buyers that they will get their house in six months, they should give the realistic picture and let the clients decide whether or not they want to wait that long BEFORE they hand over the non refundable reservation fee.
Also, during our meeting with Avida last year, we were told that the sales department has a different take on what's supposed to happen which is contrary to the rules set up by the head office. First of all, the sales department and the head office must be in sync with what they tell the customers. As we mentioned to them, the sales people are the first (and sometimes) the only Avida employees that the buyers see - so they all must be on the same page.
But what really got our goat during this process was the fact the "Customer Service" personnel do not tell the truth. They say many things but none of which are true so they end up looking worse than the sales agents they're blaming.
It is our hope that this will not happen again to some other hapless buyer out there, believing the hype and handing over a lot of cash to Avida only to end up frustrated and disappointed. Avida, the houses you sell are not exactly what you call affordable - because if it were then there wouldn't be a housing backlog in this country.
The house is finished but we are not what you can call totally happy or satisfied. And if Avida thinks one bunch of flowers will make up for all the misery they have caused us, think again.
01 May 2010
Subscribe to: